The review of the CDEM Group Plan is making steady progress. Chapter 4 Readiness and Chapter 5 Response are due to go to the Co-ordinating Executive Group early next week. A copy of these chapters has been placed in the Google Group. There is still some work to do on the roles and responsibilities and the assistance of MCDEM has been sought in this area. We are very aware that other Groups are likely to cut and paste from some parts of our Plan so we better get it right!

Evan Lloyd is working on the Risk Profile chapter and Brendan Morris is working on the Recovery Manual and Recovery Chapter. The draft Communications Strategy is also going to CEG next week but this is still to be refined by the Public Information Managers.

There are a number of supporting documents still to be developed or reviewed, not least of which is the Triennial Business Plan for the Group. Still, we are on track with our project timeline.